Tom Darte Energy Center

Scope: 25 MW Peaking Plant

Client: Greenville Electric Utility System

Location: Greenville, TX

Delivery Method: General Contractor

Casey Industrial was contracted to install 3 Wärtsilä natural gas-fired engines at this 25 MW municipally-owned power plant.

Installed 12,470 linear feet of conduit, 77,565 linear feet of wire, 12,941 terminations, 145 tons of structural steel, and 4,720 linear feet of piping.